TDR
Transmission Demand Residual
Industry ReformsFixed daily charges for TNUoS introduced in April 2023, replacing the variable Triad-based system - your band (1-4) is determined by your Maximum Import Capacity (MIC) and voltage level.
The Transmission Demand Residual (TDR) is the main component of TNUoS charges since the Targeted Charging Review (April 2023). It replaced the old Triad-based system with fixed daily charges based on capacity bands.
How TDR Actually Works:
TDR uses 4 bands per voltage level, with band determined by your Maximum Import Capacity (MIC) agreed with your DNO. Band thresholds are set by NESO using percentiles (40th, 70th, 85th) of GB-wide capacity data.
RIIO-2 Thresholds (April 2023 - March 2026, superseded):
| Voltage | Band 1 | Band 2 | Band 3 | Band 4 |
|---|---|---|---|---|
| LV | up to 80 kVA | 81-150 kVA | 151-231 kVA | over 231 kVA |
| HV | up to 422 kVA | 423-1,000 kVA | 1,001-1,800 kVA | over 1,800 kVA |
| EHV | up to 5,000 kVA | 5,001-12,000 kVA | 12,001-21,500 kVA | over 21,500 kVA |
LV No MIC sites are banded by annual consumption (kWh) instead.
RIIO-3 Changes (April 2026 - March 2031):
Rates nearly double AND thresholds shift:
| Voltage | Band 1 | Band 2 | Band 3 | Band 4 |
|---|---|---|---|---|
| LV | up to 90 kVA | 91-150 kVA | 151-250 kVA | over 250 kVA |
| HV | up to 500 kVA | 501-1,100 kVA | 1,101-2,000 kVA | over 2,000 kVA |
| EHV | up to 3,500 kVA | 3,501-11,000 kVA | 11,001-20,000 kVA | over 20,000 kVA |
Critical Warning: EHV thresholds decreased in RIIO-3. An EHV site whose average agreed capacity over the allocation window (1 May 2022 to 30 April 2024) was 4,000 kVA moved from Band 1 to Band 2 automatically on 1 April 2026, an increase in TNUoS residual of up to 767.0%.
Reducing MIC does not move your band before 2031:
Many businesses over-specified their MIC for headroom, and under TDR that lands them in a higher band. DCUSA Schedule 32 ¶4.5 holds a Final Demand Site in its charging band for the duration of the price control period, so a RIIO-3 band stands until 31 March 2031 whatever happens to the MIC. A capacity reduction still cuts the DUoS capacity charge in proportion from the date the DNO registers it. It does not change the TDR band. The one mid-period route that turns on capacity, ¶6.1(b), needs a change of use or site configuration, a capacity change of more than 50.0% against the MIC held on 30 April 2024 (¶6.3(a)), and a signed letter from a company director (¶6.2).
Two dates that matter: your DNO takes the MIC snapshot for the RIIO-4 allocation in January 2029 (¶3.1), so a reduction registered before then sets the next band. And if the RIIO-3 allocation itself was wrong, a ¶7 dispute rebates up to six years (five in Scotland) from the first incorrect charge (¶7.17). A ¶6 request only rebates from the date the DNO received it (¶6.4).
What changed on 1 April 2026: RIIO-3 rates nearly doubled, and EHV sites averaging 3,500 to 5,000 kVA over the allocation window moved up a band. Those allocations hold to 31 March 2031.
Example
HV site with 600 kVA average MIC over the allocation window = HV Band 2 under RIIO-3 thresholds, held to 31 March 2031Related terms
Put this into practice
Explore EnergyCode's charge tools to model DUoS, TNUoS, gas transportation and policy costs against your own sites.
Request a Demo