Skip to main content
Multi · Consultants

Capacity Optimiser

Right-size agreed capacity against measured peak. One kVA change, priced on the DUoS capacity charge, with the TNUoS TDR band you hold to 2031 shown beside it.

For energy consultants and operators reviewing existing HV and LV connections.

Try Capacity Optimiser
Capacity Optimiser · results

Save £35,036 over 3 years

Right-size your agreed capacity to 420 kVA

2026-272027-282028-293-Year Total

Distribution

£60,408 → £25,371

saves £35,036

Transmission

HV Band 2, held to 31 March 2031

no change

Capacity options

Cost at a range of agreed capacities

Savings

Distribution and transmission combined

£35,036

Assumptions & Methodology

Data sources and calculation methods

The journey

Four steps, one kVA figure

From MPAN and measured peak to one recommended capacity, with the distribution savings year by year and the transmission band the site holds to March 2031.

1

Enter

Enter capacity and peak

Your MPAN sets the voltage level, so the tile is already fixed to what we decoded. Add the agreed capacity from your connection agreement and your highest measured demand over the last twelve months, in kVA or kW. A 5.0% safety margin above the peak is applied by default.

Step 1 · Input panel
Voltage level

Low Voltage

Up to 1kV

High Voltage

1kV to 22kV

Extra High Voltage

22kV and above

Set from your MPAN: High Voltage

Agreed capacity (MIC)
1,000kVA
Measured peak demand
400kVA
Peak unit
kVAkW
Optimise
2

Distribution

Price the distribution leg

The DUoS capacity charge is your agreed kVA at the DNO capacity rate, every day of the year. Current and recommended sit side by side at the published rate, then the year table shows what each costs across every charging year we hold rates for.

Step 2 · Distribution

Distribution

£60,408 → £25,371

saves £35,036

Current capacity

Capacity
1,000 kVA
Daily Rate
5.31p/kVA/day
3-Year Cost£60,408
Recommended

Recommended capacity

Capacity
420 kVA
Daily Rate
5.31p/kVA/day
3-Year Cost£25,371
YearCurrentRecommendedSaving
2026-27£19,382£8,140£11,241
2027-28£20,440£8,585£11,855
2028-29£20,586£8,646£11,940
Total£60,408£25,371£35,036
3

Transmission

Check the TNUoS band

The same kVA sets your TNUoS demand residual band, but only when the band is allocated, and that allocation holds for the whole price control. The panel names the band you are in, what it costs each year to March 2031, and the January 2029 measurement that sets the next one.

Step 3 · Transmission

Transmission

HV Band 2, held to 31 March 2031

no change

Band held

HV Band 2

Capacity
1,000 kVA
Daily Rate
£117.15/day
Band Range
500 - 1,100 kVA
3-Year Cost£170,745

Next allocation

RIIO-4

Capacity measured
January 2029
Capacity held
420 kVA
Band Range
Not yet published
Band applies from1 April 2031
YearBandAnnual charge
2026-27HV Band 2£42,761
2027-28HV Band 2£52,933
2028-29HV Band 2£75,052
Total£170,745
4

Total

See the savings

One table carries the distribution savings year by year, and the tabs move every figure on the page to that charging year. The transmission column stays at zero until the next allocation: the DUoS savings apply once your DNO registers the new capacity, while the band you hold runs to 31 March 2031.

Step 4 · Savings
2026-272027-282028-293-Year Total

Savings

Distribution and transmission combined

£159,674
YearDistributionTransmissionTotal saving
2026-27£11,241£0£11,241
2027-28£11,855£0£11,855
2028-29£11,940£0£11,940
Total£35,036£0£35,036

Assumptions & Methodology

Data sources and calculation methods

The problem

An oversized kVA figure costs you every day, and sets your band for five years

Agreed capacity drives the DUoS capacity charge every day, and the TNUoS TDR band at each allocation. Most sites hold a figure set years ago that sits well above their real peak, and some sit under it and pay exceeded-capacity penalties instead.

Leave it and you pay the distribution charge on kVA you never draw, then carry the same figure into the January 2029 measurement that fixes your band for the next price control.

Watch the walkthrough

See the band you hold, and the one below it

Decode the MPAN, put in your agreed capacity and measured peak, and the tool prices both charges that capacity drives. Every band is costed, with the kVA change needed to reach each one.

  • DUoS and TNUoS together
  • Every band priced
  • The kVA change to reach each
  • Three year view

Why it matters

What you walk away with

Annual Savings, Year by Year

One annual figure for the capacity change on the DUoS capacity charge, with a row per charging year, so a client can see what the variation is worth before asking the DNO for it.

Target Capacity Recommendation

A recommended kVA that keeps a safety margin above measured peak, priced on the DUoS capacity charge and carried into the next band allocation.

Band Position and Thresholds

The TDR band the site holds until 31 March 2031, the kVA thresholds either side, and the January 2029 measurement that sets the next allocation.

Capacity options

Annual DUoS capacity cost at a range of agreed capacities, each option flagged for whether it still covers peak.

Built on official published rates

2,902
Tariff Rates
14
DNO Regions
5
TDR Bands
3
Voltage Levels

FAQ

Answers, before you ask

In the current price control, one. The DNO charges a daily DUoS capacity charge per kVA of agreed capacity, and a cut reduces it in proportion from the date the DNO registers the new figure. The TNUoS Transmission Demand Residual sits in a band allocated from the same kVA, but that band is fixed for the whole price control period. RIIO-3 bands run to 31 March 2031, so the band stays put when the capacity changes.

Still curious? Email hello@energycode.ai

Right-size capacity. Price the savings, check the band.

See the exact kVA to request from your DNO, what it saves on distribution, and the TDR band you hold until March 2031.